TCN rolls out 94,762 MW in Sept. – Official

Electricity-grid

Transmission Company of Nigeria (TCN)

Transmission Company of Nigeria (TCN)

The Transmission Company of Nigeria (TCN), on Tuesday said it wheeled out 94,762.9 megawatts (MW) in Sept., due to increase in generation in the last two weeks of the month.

The daily statistics of TCN operations obtained from Nigerian Electricity System Operator (SO), a section of the TCN, indicated that 30,936mw was generated from Sept. 2 to Sept. 12.

This was against the 63,826.9mw generated between Sept. 13 and Sept. 30.

The statistics indicated that power generation increased by 32,890.9mw between the two periods.

The daily power generated from Sept. 1 to Sept. 12 sold at 3,101mw, 2, 987.93mw, 2, 982.69mw, 3, 204.8mw and 2, 915.9mw.

Others are: 2, 944.4mw, 3, 050mw, 2, 943.5mw, 2, 943.1mw, 3, 017.2mw, and 3, 570.6 respectively.

It also showed that daily power generated from Sept. 13 to Sept. 30 were 3,782.9 mw, 3,274.5mw, 3,301.7mw, 3,959.9mw, 3,470.7mw, 3,659.6mw

Other are: 3,383.6mw, 3,304.6mw, 3,294.9mw, 3,665.7mw, 3,964.9mw, 3,790.1mw, 3,655.8mw, 3,409.1mw, 3,563.9mw, 3,539.1mw, 3,463.8mw and 3,306.1mw respectively.

The energy generated was transmitted to 11 distribution companies (DisCos).

The TCN said the national peak demand forecast stood at 19,100.00mw, the installed available capacity was 11,165.40mw, while the current transmission capacity and network operational capacity were 7,000 mw and 5,500.00mw respectively.

The peak generation ever attained in Nigeria was 5,222.3mw, while the maximum energy ever attained stood at 109,372.01mwh.

Meanwhile, TCN’s Managing Director, Mr Mohammed Usman, has called for a regulation by the Nigerian Electricity Regulatory Commission (NERC) to protect its transformers in the event of damage by Electricity Distribution Companies (DisCos).

Related News

Mohammed said the inability of the DisCos to invest in distribution infrastructure had resulted in the use of some of TCN’s transformers by DisCos to supply electricity.

This, he said, had sometimes resulted in the breakdown of the transformers.

“Under the grid code, everybody has their responsibility; we have our responsibility; and distribution companies have their responsibility.

“And where they fail to invest, it is not our problem that they fail to invest, but their lack of investment is affecting our system when we are connected to them.

“And that is why I am telling NERC that we are writing a petition that they are taking supply directly from our transformers in some areas because they have failed to build their own injection sub-stations.

“We are going to ask NERC to put it as a rule to say that if our transformers get spoilt because of the DisCos’ failure to invest, they are going to compensate us,” said Mohammed.

He said to boost the operations of TCN, the management decided to audit ongoing contracts, and where necessary take over the expired ones.

“Most of those contracts are contracts for supply and installation of 330Kv sub-station and they are supposed to last for 18 months.

“The one in Damaturu was awarded in 2006, it is about 12 years, this contract has expired.

“The problem TCN had in the past was that it awarded contracts to incompetent companies, but under current TCN management we have changed the way we award contracts.

“Most of our major contracts now, we have to do pre qualification, you have to be qualified first before you can even tender, so this kind of problem that we had will not continue.

“But some of the contractors that are not very difficult; we will work with them to complete the job,” said Mohammed.

According to him, TCN has attracted significant amount of investments, and that international donors are willing to provide more funding to executive more transmission projects.

This, he attributed to series of audits reports conducted by the current management of the company.

Load more